There was a meeting with the parks today to discuss what maintenance needs to be done at Charlie Vettiner.

The holes that will get the much needed attention are 1-4.

Hole 1
Gravel and mulch around the basket.

Hole 2
Gravel and mulch to create path from bridge to tee pad.

Topsoil will be sloped around tee pad to help reduce erosion that exist. Flowers and other natural plants will be placed here to help hold soil in place, as well as a possible barrier.

Picnic tabled leveled.

Hole 3
Topsoil to cover roots that are bare as you walk up the hill. Barriers will be needed to direct water flow.

Gravel and mulch around and near basket.

Hole 4
Topsoil will be sloped around tee pad to help reduce erosion that exist. A barrier will be placed to hold in place.

Gravel and mulch down fairway where dirt exist.


These are the projects that we will need help on. No dates have been set yet, and they will be announced as soon as materials to complete are ready to be delivered.